Edit General Photometric Schedule

The Edit General Photometric Schedule commands are used to modify the labels that appear on rooms on the drawing. Each row that is displayed is included as a row in the schedule. They do not correspond to columns like in other schedules. To set the width of the columns, use the two special values, Label Column Width and Value Column Width.

To edit the general photometric schedule project settings, go to

Ribbon: DME: Customization->Project Customization-> dm_elec-photo-general-schLabel General Photometric Schedule Label Group

Pulldown Menu: DM Electrical->Customization->Labels and Schedules->Project List->Edit General Photometric Schedule Project List

To edit the general photometric schedule standards settings, go to

Ribbon: DME: Customization->Master & Standards Customization-> dm_elec-photo-general-schLabelM General Photometric Schedule Label Group

Pulldown Menu: DM Electrical->Customization->Labels and Schedules->Standards and Master Lists->Edit General Photometric Schedule Standards List

General Photometric Schedule Label Display and Order Dialog Box

customization--general-photometric-schedule-label-display-and-order-dialog-box

See the Common Label and Schedule Information section for more information on using the Move Up and Move Down buttons and the Key, Label, Width, Display, and Schedule Title fields.

Values in the Key column are listed alphabetically below.

Average Foot-candles: The average foot-candle value in the photometric area.

Average to Maximum FC Ratio: The average foot-candle value divided by the maximum foot-candle value.

Average to Minimum FC Ratio: The average foot-candle value divided by the minimum foot-candle value.

Label Column Width: The width of the label column in the schedule.

Maximum Foot-candles: The maximum foot-candle value in the photometric area.

Maximum to Average FC Ratio: The maximum foot-candle value divided by the average foot-candle value.

Maximum to Minimum FC Ratio: The maximum foot-candle value divided by the minimum foot-candle value.

Minimum Foot-candles: The minimum foot-candle value in the photometric area.

Minimum to Average FC Ratio: The minimum foot-candle value divided by the average foot-candle value.

Minimum to Maximum FC Ratio: The minimum foot-candle value divided by the maximum foot-candle value.

Value Column Width: The width of the value column in the schedule.