Edit Egress Photometric Line Schedule List

The Edit Egress Photometric Line Schedule List commands are used to modify the labels that appear on egress photometric calculation line schedules on the drawing. Each row that is displayed is included as a row in the schedule. They do not correspond to columns like in other schedules. To set the width of the columns, use the two special values, Label Column Width and Value Column Width.

To edit the egress photometric line schedule project settings, go to

Ribbon: DME: Customization->Project Customization-> dm_elec-photo-egress-line-schLabel Egress Photometric Line Schedule Label Group

Pulldown Menu: DM Electrical->Customization->Labels and Schedules->Project List->Edit Egress Photometric Line Schedule Project List

To edit the egress photometric line schedule standards settings, go to

Ribbon: DME: Customization->Master & Standards Customization-> dm_elec-photo-egress-line-schLabelM Egress Photometric Line Schedule Label Group

Pulldown Menu: DM Electrical->Customization->Labels and Schedules->Standards and Master Lists->Edit Egress Photometric Line Schedule Standards List

Egress Photometric Line Schedule Label Display and Order Dialog Box

customization--egress-photometric-line-schedule-label-display-and-order-dialog-box

See the Common Label and Schedule Information section for more information about using the Move Up and Move Down buttons and the Key, Label, Width, Display, and Schedule Title fields.

Values in the Key column are listed alphabetically below.

Average Illuminance: The average illuminance value along the photometric calculation line, including vertical illuminance levels if they are enabled.

Average to Maximum Illuminance Ratio: The Average Illuminance divided by the Maximum Illuminance.

Average to Minimum Illuminance Ratio: The Average Illuminance divided by the Minimum Illuminance.

Label Column Width: The width of the label column in the schedule.

Maximum Illuminance: The maximum illuminance value along the photometric calculation line, including vertical illuminance levels if they are enabled.

Maximum to Average Illuminance Ratio: The Maximum Illuminance divided by the Average Illuminance.

Maximum to Minimum Illuminance Ratio: The Maximum Illuminance divided by the Minimum Illuminance.

Minimum Illuminance: The minimum illuminance value along the photometric calculation line, including vertical illuminance levels if they are enabled.

Minimum to Average Illuminance Ratio: The Minimum Illuminance divided by the Average Illuminance.

Minimum to Maximum Illuminance Ratio: The Minimum Illuminance divided by the Maximum Illuminance.

Value Column Width: The width of the value column in the schedule.