🧪Beta Content
This page contains information about new and/or updated features in the current beta release of ElectroBIM. For more information, visit the ElectroBIM beta page.
Update Panel Schedule
Updates a panel schedule created using the Insert Panel Schedule command to reflect changes made to the model and to the panel schedule template.
warning
Panel schedules are not automatically updated when changes are made to the model. You must manually update them, or run the Calculate Whole Project or Calculate Part of Project command, either of which also updates panel schedules as part of the calculation.
tip
You must be in a drafting view to use this command.
You will be prompted to select the panel schedule to be updated.
Select panel schedule to update, or press ENTER to update all panel schedules on this view:
The selected panel schedule, or all of the panel schedules on the view, will be updated.